A key part of
any project is preparing a good and reasonable estimate. While
not extremely difficult, it is tedious and very time consuming.
But not doing it correctly can be very painful later, especially in
the pocket book.
Other
information needed includes any location or weather related factors
(for example erecting a building in central Florida in the middle of
the summer has different requirements to erecting a similar building
in north central Colorado in the middle of the winter).
This
information will take the form of material requirements or bills of
material (BOM} and equipment/manpower requirements.
To do this with a reasonable degree of accuracy you need to
develop the following:
Equipment/Task List
Material Takeoff(s)
Resources Required
Time required
Weather and climate
Construction sequence
Equipment/Task List
TABLE xx - PIPING MATERIAL LIST
|
|
|
|
||
Item |
Size -
Description |
Units |
Qty |
Unit
Cost |
Total
Cost |
1 |
|
|
|
|
0.00 |
2 |
3/4" 800#
Gate Valve Extd body SW/SCRD |
ea |
5 |
100.00 |
500.00 |
3 |
4" 300# RF
Gate Valve Flgd |
ea |
2 |
550.00 |
1,100.00 |
4 |
4" 300# RF
Globe Valve Flgd |
ea |
1 |
650.00 |
650.00 |
5 |
|
|
|
|
0.00 |
6 |
4" Std Wt
SMLS Pipe ASTM A106-B |
lf |
90 |
7.00 |
630.00 |
7 |
|
|
|
|
0.00 |
8 |
4" Std Wt
90deg Ell LR BW SMLKS A234-WPB |
ea |
12 |
21.00 |
252.00 |
9 |
4" x 3" STD
WT COC RED BW SMLS A234-WPB |
ea |
1 |
54.00 |
54.00 |
10 |
3" 300# FLNG
RF WN STD WT A105 |
ea |
1 |
25.00 |
25.00 |
11 |
4" 300# FLNG
RF WN STD WT A105 |
ea |
7 |
35.00 |
245.00 |
12 |
4" 300# FLNG
RF WN Sch 160 A105 |
ea |
1 |
40.00 |
40.00 |
13 |
|
|
|
|
0.00 |
14 |
3/4" x 10-3
3000# SOCKOLET A105 |
ea |
5 |
25.00 |
125.00 |
15 |
4" x 8"
8" Sch 40 x 4" Sch 160 Weldolet A105 |
ea |
1 |
75.00 |
75.00 |
16 |
3/4" Plug
Rnd Bar Scrd A105 |
ea |
5 |
10.00 |
50.00 |
17 |
|
|
|
|
0.00 |
18 |
3" 300# RF
1/8" Thk Graphaite 95% Carbon filled Spiral wound w/ CS Gage
Ring, 304 ss Winidning Flexitallic Type CG |
ea |
1 |
50.00 |
50.00 |
19 |
4" 300# RF
1/8" Thk Graphaite 95% Carbon filled Spiral wound w/ CS Gage
Ring, 304 ss Winidning Flexitallic Type CG |
ea |
8 |
50.00 |
400.00 |
20 |
|
|
|
|
0.00 |
21 |
3/4" x 4
3/4" Ld Stud w/ (2) Hex Nuts A193-B7 A914-2H |
ea |
72 |
1.25 |
90.00 |
22 |
|
|
|
|
0.00 |
23 |
4" 300# RF
"T" Strainer Flgd hayward Model 91 |
ea |
1 |
900.00 |
900.00 |
|
|
|
|
|
|
|
Total |
|
|
|
5,186.00 |
TABLE xx - PIPING FIELD LABOR &
EQUIPMENT
|
|
|
|
|
||
Item |
Size -
Description |
Units |
Qty |
Labor
M/Hrs |
Total
M/Hrs |
Mobil
Equip
Cost |
1 |
|
|
|
|
0 |
0 |
2 |
3/4" 800#
Gate Valve Extd body SW/SCRD |
ea |
5 |
2.5 |
12.5 |
93.75 |
3 |
4" 300# RF
Gate Valve Flgd |
ea |
2 |
10 |
20 |
150 |
4 |
4" 300# RF
Globe Valve Flgd |
ea |
1 |
10 |
10 |
75 |
5 |
|
|
|
|
0 |
0 |
6 |
4" Std Wt
SMLS Pipe ASTM A106-B |
lf |
90 |
1.5 |
135 |
1012.5 |
7 |
|
|
|
|
0 |
0 |
8 |
4" Std Wt
90deg Ell LR BW SMLKS A234-WPB |
ea |
12 |
4 |
48 |
360 |
9 |
4" x 3" STD
WT COC RED BW SMLS A234-WPB |
ea |
1 |
4 |
4 |
30 |
10 |
3" 300# FLNG
RF WN STD WT A105 |
ea |
1 |
3.4 |
3.4 |
25.5 |
11 |
4" 300# FLNG
RF WN STD WT A105 |
ea |
7 |
4 |
28 |
210 |
12 |
4" 300# FLNG
RF WN Sch 160 A105 |
ea |
1 |
4 |
4 |
30 |
13 |
|
|
|
|
0 |
0 |
14 |
3/4" x 10-3
3000# SOCKOLET A105 |
ea |
5 |
2.5 |
12.5 |
93.75 |
15 |
4" x 8"
8" Sch 40 x 4" Sch 160 Weldolet A105 |
ea |
1 |
4 |
4 |
30 |
16 |
3/4" Plug
Rnd Bar Scrd A105 |
ea |
5 |
2.5 |
12.5 |
93.75 |
17 |
|
|
|
|
0 |
0 |
18 |
3" 300# RF
1/8" Thk Graphaite 95% Carbon filled Spiral wound w/ CS Gage
Ring, 304 ss Winidning Flexitallic Type CG |
ea |
1 |
2 |
2 |
15 |
19 |
4" 300# RF
1/8" Thk Graphaite 95% Carbon filled Spiral wound w/ CS Gage
Ring, 304 ss Winidning Flexitallic Type CG |
ea |
8 |
2 |
16 |
120 |
20 |
|
|
|
|
0 |
0 |
21 |
3/4" x 4
3/4" Ld Stud w/ (2) Hex Nuts A193-B7 A914-2H |
ea |
72 |
1 |
72 |
540 |
22 |
|
|
|
|
0 |
0 |
23 |
4" 300# RF
"T" Strainer Flgd hayward Model 91 |
ea |
1 |
10 |
10 |
75 |
|
|
|
|
|
|
|
|
Total |
|
|
|
393.90 |
2,954.25 |
TYPICAL LABOR &
EQUIPMENT USAGE
|
|
|
|
|
MHRS/ |
$ |
Equip |
Equip |
|
MHRS/ |
Equip |
DESCRIPTION |
CREW |
EQUIP |
COMMENT |
UNIT |
UNIT |
Mhr |
Use % |
$/hr |
UNIT |
UNIT |
$/hr |
MECAHNICAL |
|
|
|
|
|
|
|
|
|
|
|
Air
compressor |
C-35 |
E-15A |
|
ton |
20 |
45.63 |
0.25 |
228.13 |
lb |
0.01 |
0.114 |
Air blower |
C-35 |
E-15A |
100 - 1000
cfm |
ton |
20 |
45.63 |
0.1 |
91.3 |
lb |
0.01 |
0.046 |
Air blower |
C-35 |
E-15A |
1000 - 20000
cfm |
ton |
20 |
45.63 |
0.15 |
136.88 |
lb |
0.01 |
0.068 |
Air blower |
C-35 |
E-15A |
> 20000 cfm |
ton |
20 |
45.63 |
0.2 |
182.5 |
lb |
0.01 |
0.091 |
Units * Mhrs/unit * $/Mhr * Equip Use % =
Equip cost
|
Rate |
|
|
|
|
|
|
|
$/hr |
C-35 |
|
|
$/hr |
E-15 |
E-15A |
Supervisor |
90 |
|
|
Air
compressor |
10 |
|
|
Formen |
60 |
1 |
|
Jackhammer |
1 |
|
|
Carpenter |
43 |
|
|
3 kW
Generator |
5 |
|
|
Finisher |
43 |
|
|
Concrete
pump |
10 |
|
|
Boilermaker |
43 |
|
|
Concrete
buggy |
2 |
|
|
Ironworker |
43 |
3 |
|
Vibrators |
2 |
|
|
Journeymen |
47 |
|
|
40T Crane |
120 |
0.125 |
1 |
Millwrights |
43 |
2 |
|
Welder |
7 |
|
|
Welder |
62 |
|
|
Hoist |
10 |
|
|
Laborers |
32 |
|
|
Elevator |
25 |
|
|
Apprentice |
36 |
|
|
Rotary Mixer |
25 |
|
|
Operators |
50 |
1 |
|
$/hr |
|
15 |
120 |
Oiler/Gradesetter |
40 |
1 |
|
|
|
|
|
Teamsters |
45 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Manhours/day |
|
64 |
|
|
|
|
|
$/Hour |
|
365 |
|
|
|
|
|
$/hr -
average |
|
45.63 |
|
|
|
|
|
The simple example given
above of erecting a building in central Florida in the middle of the
summer versus erecting a similar building in north central Colorado
in the middle of the winter can give you a feel for the impact.
You must evaluate each
type of work that is to be done in relation to the weather
conditions expected during the period of construction. The
evaluation of the expected weather enables the planner to determine
how much additional time to allow for delays.
Construction Sequence
The sequence in which
major operations are to occur is another factor to be evaluated in
estimating. The sequence of some operations like clearing or
stripping excavation for and placement of footings is obvious this
does not present a problem. Other sequencing such as materials
processing and prefabrication can not be determined until later in
the planning and estimating stage. However construction sequence has
to be considered early because some factors effecting job sequence
are present at the very beginning of planning. Among these are
drainage and availability of materials. As described above if rain
or other climatic problems will impact the early stages of the
construction some aspect for drainage of the site even on a
temporary basis must be considered. The data on availability of
materials effect job sequence. Operations depending on materials
cannot be started until they are available and on site.
During
the initial estimating the project manager will keep notes of items
that may be critical to the job. These critical items may readily be
identified when the scheduling and detail estimating is accomplished
and they are required for a detailed project schedule analysis.
Critical items may be materials equipment or manpower with
particular skills. There procurement may be important because they
are needed immediately for the job because they are not available
locally or because a long lead time for procurement maybe required.
The entire job and the note should be studied, such items tabulated,
and action taken that they will be on hand when required.
Allowances
Allowances are used for converting "neat" quantities to "actual"
quantities. An example
would be pouring a concrete slab.
No matter how careful you are, the actual excavated amounts
will be larger than the drawings show.
You will than need to backfill the hole.
The final base will probably not be perfectly level.
The costs to take the time to make it level compared to the
cost of some extra concrete will show the time to be worth more.
When the pour is made, the bottom irregularities will be
filled with concrete.
For
material such as pipe, steel, and lumber that comes in standard
sizes, figuring the optimal quantity or lengths is function of the
allowances.
Optimum Length Calculations
In the
preparation of the estimate quantities of materials such as pipe and
lumber are given x number of linear feet for a particular operation.
This material is commonly ordered by standard commercial lengths.
Although the standard lengths are generally in the range of 8
to 20 feet in 1 or 2 foot increments, it is often times better to
order shorter 8 foot 10 and 12 foot standard lengths based on ease
of handling. When this can be a length that can be utilized on the
project with minimum wastage. Or without having to be spliced into
longer lengths. In many parts of the structure or building it is
obvious what commercial lengths should be ordered for example the
chose in or 10 feet inches long 10 foot commercial lengths are
obviously needed. There are places in the building however where it
is not quite as evident what lengths should be ordered. It is then
necessary to calculate the most economical standard length that when
ordered will give the least waste. A procedure for this is as
follows:
Calculate the number of pieces per standard lengths for each of
the 3 standard lengths (8. 10 or 12), if this number is not an
integer round down.
Find
the number of standard lengths required for each of the
alternatives, if this number is not an integer round up.
Calculate the total linear feet required for each of the 3
standard lengths and use the least.
Required
25 pieces of 2” standard weight carbon steel pipe, each piece to be
3’-3 ¼” long.
Each piece length |
39.25 |
Inches |
|
|
|
Items Required |
25 |
|
|
|
|
Standard Size (ft) |
8 |
10 |
12 |
16 |
20 |
Inches/piece |
96 |
120 |
144 |
192 |
240 |
Pieces/std size |
2.45 |
3.06 |
3.67 |
4.89 |
6.11 |
Use: |
2 |
3 |
3 |
4 |
6 |
Std sizes Required |
12.50 |
8.33 |
8.33 |
6.25 |
4.17 |
Use: |
13 |
9 |
9 |
7 |
5 |
Total ft |
104 |
90 |
108 |
112 |
100 |
Needed (ft) |
81.77 |
81.77 |
81.77 |
81.77 |
81.77 |
Wastage (ft) |
22.23 |
8.23 |
26.23 |
30.23 |
18.23 |
Best fit |
|
X |
|
|
|
TYPE OF ESTIMATE
VERSUS CONTINGENCY AND EXPECTED ACCURACY |
|||||
|
|
|
|
|
|
DESCRIPTION |
CLASS |
% OF TOTAL ENGINEERING |
PROBABLE CONTINGENCY % |
ACCURACY OF ESTIMATE % |
|
|
|
|
(w/ Historical Data) |
(w/o Historical Data) |
|
|
|
|
|
|
|
Bid |
|
100 |
3 |
5 |
+/- 5 |
|
|
|
|
|
|
Engineers |
I |
75 - 100 |
5 |
10 |
+/- 5 |
|
|
|
|
|
|
Definitive |
II |
40 - 75 |
10 |
15 |
+/- 7.5 |
|
|
|
|
|
|
Preliminary |
III |
15- 40 |
15 |
20 |
+/- 10 |
|
|
|
|
|
|
Conceptual |
IV |
2 - 15 |
20 |
25 |
+/- 15 |
|
|
|
|
|
|
Magnitude |
V |
0 - 2 |
25 |
35 |
+/- 20 |
CONSTRUCTION ESTIMATING SOFTWARE
Many
professional estimators use their own estimating tools, which are
normally a database of labor rates and equipment usage rates for
various tasks and a spreadheet form to automate the calculations.
This allows them to tailor their estimates to fit each job.
This does lead to a lack of uniformity between any two
estimators. Because of
this some companies have turned to prepackaged estimating tools.
Doing a search on the internet will find many options, but this is a dynamic environment and any list is out of date as soon as it is posted.
Good luck and happy estimating.
o
40+ years’ experience in the mining industry with strong mineral
processing experience in precious metals, copper, industrial
minerals, coal, and phosphate
o
Operational experience in precious metals, coal, and phosphate plus
in petrochemicals.
o
Extensive experience performing studies and determining feasibility
in the US and international (United States, Canada, Mexico, Ecuador,
Columbia, Venezuela, Chile, China, India, Indonesia, and Greece).
o
E-mail:
info@smartdogmining.com