Earthmoving in Mining Operations
Chapter 5: HYDRAULIC EXCAVATORS
Hydraulic excavators are designed to excavate below the ground
surface on which the machine rests. These machines have good
mobility and are excellent for general-purpose work, such as
excavating trenches and pits.
Because of the hydraulic action of their stick and bucket
cylinders, they exert positive forces crowding the bucket into the
material to be excavated.
The major components of the hydraulic hoe are the boom, the
stick (arm), and the bucket.
DESCRIPTION
Fast-acting, variable-flow hydraulic systems and easy-to-operate
controls give hydraulic excavators high implement speed and breakout
force to excavate a variety of materials. The hydraulic hoe is ideal
for excavating below the ground’s surface on which the machine
rests. A large variety of booms, sticks, buckets, and attachments
give these excavators the versatility to excavate trenches, load
trucks, clean ditches, break up concrete, and install pipes.
Large excavators (Figure 5-1) can handle large volumes.
The small excavators (Figure 5-2) can work in tight
places and has good mobility
Figure 5-1. Large Excavator
Figure 5-2. Small Excavator
EXCAVATION TECHNIQUES
The hoe is normally associated with two types of
excavations¾trenching (linear-type) and basement (area-type). The
operator should judge the length and depth of cut to produce a full
bucket with every pass (Figure 5-3).
Figure 5-3. Hoe-Bucket Operating Dimensions
TRENCHES
Figure
5-4
shows parallel and perpendicular trenching using hoe attachment.
Figure 5-4. Digging Trenches With a Hoe Attachment
Parallel
With the parallel method, center the hoe on the trench, while
keeping the tractor in line with the trench center line. As the
digging progresses, move the machine away from the excavation and
load the material into haul units or stockpile it along the side of
the trench for later use as backfill.
Perpendicular
When using the perpendicular method, dig the trenches in two
or more cuts or lifts. To excavate the top 35 to 45 percent of the
trench depth, make the first cut with the boom carried high. To
finish the cut and remove the remainder of the material, move
forward about one-half the length of the machine with the boom
carried low. Although this method involves more and shorter moves,
it has better bucket digging angles and shorter hoisting distance on
the top lifts.
CONTAINMENT/PONDS
Many variations of the two excavation sequences shown in
Figure 5-5 are possible. The procedures vary with the design and
shape of the excavation, the restrictions of surrounding properties,
and the requirements for disposing of the spoil. The first cut is a
trench with vertical outside walls.
To minimize handwork or cleanup, dig all outside wall faces
vertically. Plan the starting point and the digging sequence so that
the machine conveniently works itself out of the excavation. Dig
trenches for service pipes last; dig them from the basement outward.
Straddle the machine over the outer edge and dig over the end and
side of the tractor. Move the machine as the arrows in the figure
indicate.
Figure 5-5. Two Methods of Excavating Containment/Ponds
OPERATION TECHNIQUES
Underground Utilities
Survey the area for underground hazards as well as for
surface obstacles before digging. This applies particularly to
populated areas with multiple underground utilities.
Confined Quarters
Working in confined quarters is not efficient from a
production standpoint. If expecting considerable close-quarter work,
plan to use small machines that can operate efficiently with a
minimum work radius.
Drainage Ditches
If the job is to continue during wet seasons or in wet areas,
give prime consideration to drainage. Begin ditch excavations at the
lower end and work toward the upgrade.
Hard Materials
A
hoe will dig into fairly hard materials. However, blasting or
ripping may be more efficient than breaking through hardpan and rock
strata with the bucket. Once the trench is open, break the ledge
rock by pulling the bucket up under the layers. Remove the top
layers first, lifting only one or two layers at a time.
SMALL EXCAVATOR WITH A LOADER BUCKET
A small excavator is generally a lightweight, skid-steer,
diesel-engine, high-mobility machine. It is equipped with a hoe, a
loader bucket, and other hydraulic attachments.
TRACK-MOUNTED EXCAVATOR
Track-mounted excavators (Figure 5-6) are
diesel-engine machines that have a maximum digging depth of
approximately 20 feet and an approximate dumping height of 22 feet.
These excavators can travel around a job site at a maximum speed of
about 3 mph in high range. They must be transported for
long-distance travel between projects. They are used for excavating
pipeline trenches, drainage ditches, building footings, and hasty
fortifications and for loading trucks.
Figure 5-6. Track-Mounted Excavator
EXCAVATING
An excavation cycle consists of loading the bucket, swinging
the loaded bucket, dumping the bucket, and swinging the empty
bucket. Average conditions would be a depth of cut between 40 and 60
percent of the machines rated maximum digging depth and a swing
angle of between 30° to 60°.
Greater digging depths or swing angles increase the cycle
time.
Make sure the hoe is level before operating. Lower the front
loader bucket to the ground (flat) so that the machine’s front
wheels are not in contact with the surface. Move the gearshift and
the range-shift levers to their neutral positions, and lower the
outriggers. Use the outriggers to level the machine and to raise the
rear wheels slightly above the ground. Always operate with the least
amount of bucket-arm swing.
For evaluating heaped capacity, hoe buckets are rated with an
assumed material repose angle of 1:1. Therefore, actual bucket
capacity depends on the type of material being excavated as all
materials have their own natural repose angle. Table 5-1
provides bucket fill factors for hoe buckets based on material type.
Table 5-1. Bucket Fill Factors for Hoe Buckets
|
Material
|
Fill Factor Percent*
|
Moist loam or sandy clay
|
1.00 to 1,10
|
Sand and Gravel
|
0.95 to 1.10
|
Blasted rock:
|
|
Well blasted
|
0.60 to 0.75
|
Average
|
0.50 to 0.60
|
Poor
|
0.40 to 0.50
|
Hard tough clay
|
0.80 to 0.90
|
*Decimal of heaped-bucket capacity, for adjustment to LCY
|
|
Cyle time is mostly dependent on size of bucket, which
idefines swing radius.
Table 5-2. Average Cycle Times for Excavators
|
Excavator Size,
|
|
Heaped-Bucket Capacity
|
|
(Cubic Yards)
|
Cycle Time (Minutes)
|
Under 1.0
|
0.25
|
1.0 to 5.0
|
0.3 to 1.0
|
Over 5.0
|
1.0 to 1.5
|
NOTE: Includes load, maneuver with four reversals of
|
direction (minimum travel), and dump.
|
Bucket Cylinder.
When using the bucket cylinder to excavate, follow these steps
(Figure 5-7):
Step
1.
Put pressure on the boom to force the bucket teeth or cutting edge
into the ground.
Step 2.
Roll the bucket toward the machine until it is full.
Step 3.
Raise the bucket, in a smooth operation, high enough above the
trench to clear the spoil pile or the hauling unit, and dump the
excavated material.
Figure 5-7. Bucket-Cylinder Operation
Stick
Cylinder. The maximum digging force is developed by operating
the stick cylinder perpendicular to the stick. As a rule, the
optimum depth of cut for a hoe is 30 to 60 percent of the machine’s
maximum digging depth (Figure 5-3). When using the stick
cylinder to excavate, follow these steps: (Figure 5-8).
Step
1.
Lower the bucket into the digging position
Step 2.
Roll the bucket until the bucket teeth or the cutting edge is flat
on the ground Step 3. Use the stick cylinder to move
the bucket toward the machine until it is half full Step 4.
Raise the stick and roll the bucket until it is full
Figure 5-8. Hoe Digging Technique
Loader Bucket
When digging with a loader bucket:
-
Use the bucket cylinders to help break the ground loose instead
of depending on the forward movement of the machine, as in the
loader crowding technique.
-
Do not raise the bucket higher than necessary to dump the
material.
-
Use as flat a ramp as possible when starting an excavation. Plan
the job so that most of the hauling from the excavation can be
done when driving the unit forward. A steeper ramp can be used
when driving forward than when driving in reverse.
-
Keep the working area level.
LOADING
To excavate and load, a hoe bucket must raise through the
digging motion and above the haul unit. If possible, spot the truck
on the pit floor. The bucket will then be above the haul unit when
the digging is complete. At that point it is not necessary to raise
the bucket further before swinging and dumping. This arrangement
will save about 12 percent of the total excavation loading cycle
time. When loading dump trucks with a hoe:
-
Plan and lay out the area of operation.
-
Spot the truck so that the hoe does not have to turn (revolve)
more than 90° (V-positioning, discussed in Chapter 10, is
often appropriate
Rotate the bucket over the rear of the dump bed, rather than
over the cab of the truck.
-
Keep the working area smooth.
-
Raise the bucket while moving toward the truck.
-
Lower the bucket while moving away from the truck.
-
Shake the bucket only when necessary to loosen dirt stuck in the
bottom of the bucket.
TRENCH
BACKFILLING
Use the loader bucket for trench backfilling as follows:
-
Position the machine at approximately a 45° angle to the length
of the trench and its spoil pile.
-
With the bucket raised about 2 inches above the natural ground,
use it like a dozer blade to push the material into the trench.
Keep the bucket level
while pushing the material; do not crowd/curl. After the
material falls into the trench, reverse the machine and move
along the pile to repeat pushing.
-
After the last pass, dump the material remaining in the bucket
into the trench. If the material in the spoil pile along the
trench is higher than 2 feet or is wet, attack the pile in two
passes. Take off the upper half with the first pass and the
remainder with a second cleanup pass.
LIFTING
On utility jobs the excavator many need to lift and swing heavy
sections of pipe into a trench. Sometimes these machines are used to
hoist and unload materials from trucks. The weight an excavator can
lift depends on the distance the load is from the center of gravity
of the machine. Always refer to the current specification sheets
before attempting a lift. Position the machine as close to the load
as possible. The other critical element to consider is swing and
position. The lifting capability is 65 to 70 percent greater over
the front of the machine than over the side. These machines are
designed to handle 15,000 pounds (at a swing radius of 15 feet) over
the side.
PRODUCTION ESTIMATES
Factors that affect hoe production are the:
-
Width of the excavation.
-
Depth of the cut.
-
Material type.
-
Working radius for digging and dumping.
-
Required bucket dumping height.
EXAMPLE
Use
a hoe equipped with a 0.25-cubic-yard bucket to excavate hard clay.
The depth of cut will average about 50 percent of the machine’s
maximum digging depth and the swing angle should be less than 60°.
What is the expected production, in BCY per hour, assuming 50
working minutes per hour?
Step 1.
Determine the bucket fill factor based on the material type (Table
5-1).
Fill
factor for hard clay = 0.8 to 0.9 (80 %to 90%)
Lacking
any other information, use an average of
0.85 (85 %).
Step
2.
Use a hoe cycle time based on past performance data if available or
use the average cycle time from
Table 5-2.
Average
cycle time = 0.25 minute (15 seconds)
Step 3.
Determine the ideal production rate (LCY per hour).
Ideal
production rate (LCY per hour) =
Step
4.
Determine the production rate (LCY per hour) by adjusting for
efficiency.
Step 5.
Convert the production rate from LCY per hour to BCY per hour.
Determine the soil-volume correction factor from Table 1-2.
Back to the
Notebook Page